An international POS rollout is about much more than producing the right number of display units. When deployments run simultaneously across multiple markets, what matters is structural feasibility, consistency, logistics, installation method and control over the entire process. In fact, the most expensive mistakes are often made before production even begins.
Warren’s specialises in the design, engineering, production and international logistics of POS materials. Rafał Kowalczyk, Managing Director of Warren’s, spoke with OOH Magazine about how to prepare a project for scaling and how to reduce risk during European rollouts.
The most expensive mistakes happen before production
In large POS projects, it is easy to assume that the greatest risk arises at the production stage. In practice, many problems begin much earlier: during brief evaluation, concept development, structural design or material selection.
A single decision rarely leads straight to a serious problem. Far more often, it is the sum of seemingly minor oversights. A material may be unsuited to the planned production run, a structure may prove harder to manufacture, the packaging method may increase transport costs, and the schedule may not allow time for prototype validation.
With a single unit, some of these issues can still be corrected easily. With several hundred or several thousand units, every change can mean a real cost and affect the delivery date.

“The most expensive mistakes in POS projects are often made before production even starts. That’s why we review concepts in terms of structure, specified materials and logistics before any decision on scale is made.”
Rafał Kowalczyk, Managing Director
This is exactly why the pre-production stage matters so much. The earlier a project’s technological and logistical feasibility is verified, the lower the risk of costly changes once the production run has started.
Rolling out POS in one market and rolling out the same solution across several or a dozen countries are two different levels of complexity.
A European rollout adds the need to maintain consistency at a larger production scale, plan transport, adapt the process to different locations and ensure the right installation standard. The project must therefore be designed not only for how it looks, but also for whether it can be consistently manufactured, packed, shipped and installed in many places.
This is especially important for multi-material constructions. Wood, metal, plastics, print and electronic components may each require different technologies and processing methods. If they are not properly coordinated at the design stage, problems may only surface during series production, transport or installation.
That is why at Warren’s the process runs from brief and concept, through prototyping and production, all the way to implementation. This model makes it possible to check the dependencies between stages early, rather than solving problems once the project is already at scale.
This approach matters not only for quality. Early validation also affects budget and schedule. If the structure, materials, packaging and installation method are optimised before the series begins, it is easier to predict the real cost of the project and plan its delivery.
Budget, quality and time: three variables of one process
In international POS rollouts, it is hard to treat budget, quality and lead time as three independent areas.
Changing a material can affect production cost. A different packaging method can change transport cost. A more complex structure can lengthen installation. Conversely, an attempt to shorten lead time may require additional production or logistics resources.
That is why cost control should begin before production.
Warren’s bases its operating model on continuous control of these three variables at every stage of the project: budget, quality and lead time.
This matters especially because material cost is only one component of a project’s total cost. In a large rollout, packaging, warehousing, transport, installation and any rework also play a part.
That is why POS design should take into account the entire life cycle of the material, from production, through logistics, to implementation in a store or other location.
Series production requires consistency, not just capacity
At large scale, having the right production facilities alone does not solve the problem. What matters is whether the entire process allows consistency to be maintained.
Warren’s carries out most of its production processes in its own facility, with 2,000 m² of production space and 1,500 m² of warehouse space. The team includes designers, engineers, project managers, carpenters, welders, electricians and installers, and production covers wood, metal, plastics, print and assembly, among others.
This combination of capabilities makes it possible to control the dependencies between successive stages. This is particularly important for POS materials, which must later function outside the production environment. The structure has to survive transport, be installed efficiently, and retain its intended appearance and functionality after implementation.
That is why quality control should not begin only when the finished product is accepted. It should accompany the entire process.
A European rollout begins where production ends
Manufacturing the materials is only the beginning of the journey.
An international rollout also requires proper planning of warehousing, transport, deliveries to specific locations, installation and completion reporting. The more markets and points of sale, the more coordination matters.
At Warren’s, project management is based on a single source of information about tasks, responsibilities and deadlines. The team uses ClickUp to manage schedules, define dependencies and report progress, while a proprietary app is used to coordinate field implementation. It makes it possible to track completion status at individual locations and to collect photo documentation, installation confirmations and issue reports.
With a large number of locations, this kind of process visibility becomes especially important. It is not just about the final report. Being able to monitor progress during delivery makes it possible to spot problems earlier and respond before they affect the final deadline.
A multi-market rollout requires more checks, but it should not mean more unknowns.
This is one of the most important principles drawn from Warren’s experience.
XGIMI: over 450 locations and various store formats
A good example of the scale of an international rollout is the display unit rollout for the XGIMI brand.
The project was delivered in France and covered more than 450 locations across the FNAC, Darty, Boulanger and E.Leclerc chains. The display had to showcase several devices, allow for interchangeable product communication, and maintain visual consistency across different store formats.
This is an example of a project where simply producing the right number of displays would not have been enough.
The structure had to be designed for series manufacturing, transport and implementation across many locations. At the same time, the end result had to maintain the intended standard regardless of the specific store format.
It is in projects like this that the value of early validation, proper production preparation and implementation control becomes clear.

Experience across many countries changes the way POS is designed
Over the past 10 years, Warren’s has delivered projects in more than 30 countries, working with international brands from the electronics, spirits and FMCG sectors. Its portfolio includes Jack Daniel’s, TCL, Dewar’s, XGIMI, Beefeater, G.H. Mumm, Finlandia Vodka, Xiaomi, Adamed, Coca-Cola HBC, LECH and Huawei. This experience makes it possible to view a rollout not only from the perspective of a single product, but of the entire process.
Different markets mean different delivery conditions, but the goal remains the same: maintain quality, control costs and complete the rollout on schedule. That is why the larger the project, the more important it is to prepare it before production begins.
It is not about eliminating every possible problem. It is about making sure most potential problems are spotted while it is still easy to respond to them.
International POS rollouts need to be thought through earlier
The biggest shift in approaching large POS projects begins with moving responsibility for risk earlier in time. Instead of waiting for production to find out whether a concept is feasible, it is worth verifying it earlier. Instead of analysing logistics after production is complete, it is worth factoring it in during design.
Instead of reviewing a rollout only after it is finished, it is worth having access to real-time information on its progress. And instead of treating budget, quality and deadlines as separate issues, it is worth managing them as three elements of a single process.
It is precisely this approach that makes it possible to reduce risk in large-scale projects.
Warren’s in OOH Magazine
Rafał Kowalczyk, Managing Director of Warren’s, spoke in more detail about how Warren’s prepares and manages international POS rollouts in an interview with OOH Magazine.
The full interview covers topics including pre-production engineering, multi-material manufacturing, organising European rollouts, project management tools, field reporting and the delivery of the XGIMI project.
POSM that arrives after the campaign is not just late material. It is an unused part of the marketing budget.
Planning a POS rollout?
If your project spans multiple markets, locations and store formats, it pays to plan the process before series production begins.
Warren’s combines design, engineering, production and international logistics for POS materials, supporting brands in delivering projects from brief and prototype through to implementation.
Let’s talk about your project.

Rafał Kowalczyk
Posiada dwudziestoletnie doświadczenie w sprzedaży oraz w prowadzeniu projektów związanych z rozwojem i produkcją materiałów POS. Karierę rozpoczął od pracy w międzynarodowej organizacji, gdzie prowadził zespół sprzedażowy, który obsługiwał globalne korporacje. Doświadczenie zdobywał również w mniejszej firmie, ucząc się szybkiej reakcji na zmieniające się potrzeby klientów oraz elastycznego zarządzania zasobami. Jego pasją jest pozyskiwanie nowych klientów i rynków. Zdobyte doświadczenie wykorzystuje na stanowisku Managing Directora w firmie Warren’s.